Table 1.

Calculated Labor for Establishing a Computerized Inventory for 10,000 Trees Using Data Developed from Fort Worth Study

ItemPerson-hours (PHRS)PHRS PER TreeLabor Cost of $5.00/hr. wage
Pre-inventory training time for data collection persons (2 persons × 4 hours/person)8.0008$0,004
Travel to and from beginning and end of data collection (½ hr/day × 2 persons × 48 days)48.00480.024
Labor required to record data on data collection sheets (48 days × 8 hrs/day × 2 persons)768.07680.384
Labor required to digitize information (30 sec/tree × 10,000 trees ÷ 3600 sec/hour)84.00840.042
Labor required to key-punch data (15 sec/tree × 10,000 trees ÷ 3600 sec/hour)42.00420.021
TOTAL950.0950.475