Table 1. Example of man-hour estimating
TaskFactorMan hoursCrew membersMan hours
1. Job assignment, etc.Fixed .5 21.0
2. Travel time, etc.Var. .75 21.5
3. Work site organization, etc.Fixed .252 .5
4. Medium prune 16” oakFixed2.1 12.1
5. Medium Prune 30” mapleFixed5.2 15.2
6. Clean UpFixed .5 21.0
7. Disposal of debrisVar.1.0 22.0
8. Travel time, etc.Var. .75 21.5