Table 1.

1973-1981; Actual tree-work completed projected to all tree-work to be done

Div.Trees maintainedPole-miles maintainedAve. trees per pole-mileTotal pole-mile(3) Percent of pole-miles by divisionTotal trees to be maintained(1) Percent of tree-work by division
Central261,3642,2371172,95227.0%345,38426.5%
Lebanon127,8812,335551,50513.8%82,7756.4%
Eastern245,8411,3971762,38421.7%419,58432.2%
Western371,4063,3551 114,09637.5%454,65634.9%
Company1,006,4929,32410810,937100.0%(1,302,399)100.0%