- Table 1.
Calculated Labor for Establishing a Computerized Inventory for 10,000 Trees Using Data Developed from Fort Worth Study
Item Person-hours (PHRS) PHRS PER Tree Labor Cost of $5.00/hr. wage Pre-inventory training time for data collection persons (2 persons × 4 hours/person) 8 .0008 $0,004 Travel to and from beginning and end of data collection (½ hr/day × 2 persons × 48 days) 48 .0048 0.024 Labor required to record data on data collection sheets (48 days × 8 hrs/day × 2 persons) 768 .0768 0.384 Labor required to digitize information (30 sec/tree × 10,000 trees ÷ 3600 sec/hour) 84 .0084 0.042 Labor required to key-punch data (15 sec/tree × 10,000 trees ÷ 3600 sec/hour) 42 .0042 0.021 TOTAL 950 .095 0.475